Goal: Embrace healthy community growth by building, maintaining and continuously improving our municipality-owned infrastructure.

Goal#1: Safe and Reliable Infrastructure

Strategic Priorities and Actions
1.1: Taking and Evidence-based Approach to Infrastructure Renewal Projects
  • Work with the County to establish South Stormont Growth Priorities that identify zones and timelines for settlement expansion (Winter 2024)
 
  • Complete an Asset Management Plan for non-core assets. (Spring 2024)
 
  • Establish prioritized list of road reconstruction projects based on Asset Management Plan. (Summer 2025)
 
  • Work with the County to identify options and costs for improvements to County Roads 14 and 36. (Fall 2025)
1.2: Expanding Water and Wastewater Systems to Accommodate Growth
  • Work with the development community to advocate for upper levels of government funding for water/wastewater system expansion. (Spring 2024)
 
  • Determine potential options and a phased approach with costs for alternative short-term water/wastewater solutions, including discussions with the City of Cornwall about connecting to their water/wastewater systems. (Spring 2024)
 
  • Initiate public education campaign to stress the importance of water conservation. (Fall 2023)
1.3: Optimizing the Delivery of Essential Services by Maintaining and Upgrading our Facilities and Equipment
  • Complete and Accessibility Plan that established risk-based accessibility priorities and an implementation sequence/timeline within budget and staffing constraints. (Fall 2026)
 
  • Complete condition assessment for all Township-owned buildings, including cost estimates and priorities. (Spring 2024)
 
  • Engage an architect/engineering firm to work with Township staff to produce concept plans with cost estimates to modify Township Hall for use by Township staff; expand Council Chambers; and upgrade the arena to include a community hall. (Fall 2025)
 
  • Finalize location and engage and architect/engineering firm to work with Township staff to produce a concept plan and cost estimate for a new fire hall. (Spring 2024)
 
  • Prepare final design drawings for new fire hall (Winter 2025); tender for construction (Winter 2025 - Spring 2026); and build new fire hall. (Fall 2026)
 
  • Work with the County to explore transitioning to regional waste collection. Identify local property and/or resources that South Stormont could offer to support this transition. (Spring 2025)

Contact Us

Township of South Stormont
2 Mille Roches Road, Long Sault K0C 1P0


(613) 534-8889
info@southstormont.ca

Get Township news right to your inbox!

Stay up to date on the Township's activities, events, programs and operations by subscribing to our News and Notices.

This website uses cookies to enhance usability and provide you with a more personal experience. By using this website, you agree to our use of cookies as explained in our Privacy Policy.